Corcoran Water Tower

Plat Location at Hope Church

Update: June, 2023. The contractor has begun excavation at the water tower site for the foundation in late May/early June. Initial erosion control measures and excavation activities will begin shortly with a significant amount of work to be completed on the tower foundation before the structure can be erected. 

Overview
On October 27, 2022, the City Council approved a site plan, preliminary plat, and variance request for the City's first water tower. The location of this project is on the south side of 19951 Oswald Farm Road (Hope Community Church).

The approval and construction of this water tower is planned to coincide with the construction of the City's first Water Treatment Facility (located at 10120 County Road 116).
Rendering of a possible 750,000 gallon tower

Tower Design

The tower body is designed to be constructed with a steel body and will hold 1,000,000 gallons of water. The tower will be 156 feet in height, 28 feet in diameter, and 62 feet in diameter at it's widest point.

Final paint colors and logo details will be approved by the City Council in the Summer of 2023. 


Preliminary and Final Plat
The City and Hope Community Church agreed to split the property at 19951 Oswald Farm Road into 2 separate parcels, with the Water Tower being located on a 1.2 acre lot located on the south side of the property. 


Variance
On October 27, 2022, the City Council approved three variances for this project. These included:
-A variance from the minimum lot size for the Public/Institutional District from 20 acres to 1.2 acres.
-An overhead door to be placed where it can be visible from the County Road. 
-A drive aisle of 37 feet from the lot line was allowed where 50 feet would be required in the Public/Institutional District. 

Previous Meeting Dates

March 9, 2023 City Council
October 6, 2022 Planning Commission
October 27, 2022 City Council

City of Corcoran | All Rights Reserved | Powered by CivicLive | © 2024 Civiclive.